Empire Wind 1
816 MW generation in Kings, NY · In queue since June 2018 · Proposed COD July 2027
816 MW
Capacity
1
Components
Offshore Wind
8y 5m
In Queue
System Impact Study
IA Phase
Signed Feb 2021
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 8m
IA → COD
6y 5m
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Interconnection Queue; status 12
Project under construction
Typical: 36–60 months
Proposed COD: 2027-07-01
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
medium confidence at research time
- renewablesnow.com/news/court-lifts-construction-ban-on-equinors-empire-wind-off-new-york-1288060/
- reuters.com/business/energy/us-pausing-five-offshore-wind-projects-over-national-security-concerns-burgum-2025-12-22/
- nyserda.ny.gov/All-Programs/Offshore-Wind/Focus-Areas/NY-Offshore-Wind-Projects
- news10.com/news/empire-wind-1-construction/
- gcaptain.com/new-york-files-lawsuit-to-restart-empire-wind-as-5-3b-project-nears-collapse/
Commercial operation date: None of the news facts or search snippets gives a post-LBNL COD. The LBNL proposed_cod of 2027-07-01 is the only date available. The stop-work and lease-suspension episodes in 2025-26 are a schedule risk, but no revised date was found.
Developer: LBNL lists the project LLC 'Empire Offshore Wind LLC'. News extraction (Renewables Now, 2026-01-16, 2 of 4 articles supporting) names Equinor as the developer, so the LLC appears to be Equinor's project vehicle. No ownership change is documented in the provided sources.
Status: NYSERDA lists Empire Wind 1 as under construction. Reuters (2025-12-22) reports the lease suspension for projects under construction, and Renewables Now (2026-01-16) reports the court lifting the construction ban. LBNL's 'active' status only reflects queue position.
About
Generated Apr 10, 2026 · Predates Sep 30, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Empire Wind 1 is a proposed 816 MW offshore wind generation project located in Kings County, New York. The project, being developed by Empire Offshore Wind LLC, entered the NYISO interconnection queue as queue ID NYISO-737 on June 12, 2018. The proposed commercial operation date is December 1, 2026, and its interconnection status is currently in the System Impact Study phase. The point of interconnection is the Gowanus 345kV substation.
The development project has been the subject of recent news coverage, with 12 articles categorized as regulatory, development, deals, and industry news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- NYISO queue source as of: Sep 30, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Kings
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Empire Offshore Wind LLC
Utility
ConEd
Entity
NYISO
Service Type
—
Point of Interconnection
Gowanus 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE J
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- GOWANUS_GT2_1
- POI Substation
- Gowanus Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all 10 articlesGeothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
KCE NY 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Max 4 Wind
Data tables and metrics from the InfraSure database.
KCE NY 31
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.