Trelina Solar Energy Center
79.8 MW generation in Seneca, NY · In queue since June 2018 · Proposed COD April 2028
79.8 MW
Capacity
1
Components
Solar
8y 1m
In Queue
System Impact Study
IA Phase
Signed Feb 2021
Queue → IA
2y 8m
IA → COD
7y 2m
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-04-01
The Trelina Solar Energy Center is a proposed 79.8 MW solar generation project located in Seneca County, New York. Developed by Trelina Solar Energy Center, LLC, the project is interconnected to the New York State Electric and Gas (NYSEG) utility. It is currently active in the New York Independent System Operator (NYISO) interconnection queue as project number NYISO-720, with an original queue entry date of June 7, 2018.
The proposed commercial operation date for the Trelina Solar Energy Center is January 1, 2025. The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the Border City - Station 168 115 KV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Seneca
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Trelina Solar Energy Center, LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Border City - Station 168 115 KV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE B
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- STA_168_34_KV_BK1_2_REV_LBMP_B
- POI Substation
- Station 168
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Trelina Solar Energy CenterForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.