Gateway Solar Energy Center
180 MW generation in St. Lawrence, NY · In queue since March 2017 · Proposed COD April 2028
180 MW
Capacity
1
Components
Solar
9y 2m
In Queue
Facility Study
IA Phase
Signed Feb 2021
Queue → IA
3y 11m
IA → COD
7y 2m
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-04-01
North Side Solar is a proposed 180 MW solar generation project located in St. Lawrence County, New York. The project, developed by North Side Energy Center, LLC, is interconnected to the NYISO grid at the Massena - Moses 230kV point of interconnection. It entered the NYISO interconnection queue as queue ID NYISO-620 on March 27, 2017, and has a proposed commercial operation date of April 1, 2028. The project's interconnection status is currently in the Facility Study phase.
The proposed project is designed as a 180 MW solar facility. The interconnecting utility is NYPA. The project is currently listed as active within the NYISO interconnection queue.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
St. Lawrence
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Gateway Solar Energy Center, LLC
Utility
NYPA
Entity
NYISO
Service Type
—
Point of Interconnection
Massena - Moses 230kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Gateway Solar Energy CenterForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.