Dog Corners Solar
20 MW generation in Cayuga, NY · In queue since November 2016 · Proposed COD April 2026
20 MW
Capacity
1
Components
Solar
9y 8m
In Queue
Facility Study
IA Phase
Signed Jun 2019
Queue → IA
2y 7m
IA → COD
6y 10m
Total Duration
2y 7m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-04-01
Dog Corners Solar is a proposed 20 MW solar generation project located in Cayuga County, New York. The project, developed by SunEast Dog Corners Solar LLC, is interconnected to the NYSEG utility via the Aurora 34.5kV point of interconnection. It is listed in the NYISO interconnection queue as queue ID NYISO-584, with an entry date of November 2, 2016. The proposed commercial operation date is April 1, 2026, and the project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 20 MW of solar photovoltaic generation. It is currently listed as an active project within the NYISO interconnection queue. The project has appeared in recent news coverage regarding renewable energy development in upstate New York.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Cayuga
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
SunEast Dog Corners Solar LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Aurora 34.5kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Dog Corners SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.