Greene County 2
10 MW generation in Greene, NY · In queue since September 2016 · Proposed COD June 2027
10 MW
Capacity
1
Components
Solar
10y 2m
In Queue
Facility Study
IA Phase
Signed Feb 2020
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 5m
IA → COD
7y 4m
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Interconnection Queue; status 11
Project under construction
Typical: 12–24 months
Proposed COD: 2027-06-01
About
Generated Apr 10, 2026 · Predates Sep 30, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Greene County 2 project is a proposed 10 MW solar generation project located in Greene County, New York. The project, developed by Hecate Energy Greene 2 LLC, is interconnected to Central Hudson Gas & Electric (CHG&E) via the Coxsackie 13.8kV point of interconnection.
The project is listed in the New York Independent System Operator (NYISO) interconnection queue as queue ID NYISO-573, with an entry date of September 6, 2016. The proposed commercial operation date is May 1, 2025. Its interconnection agreement status is currently in the Facility Study phase.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- NYISO queue source as of: Sep 30, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Greene
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Hecate Energy Greene 2 LLC
Utility
CHG&E
Entity
NYISO
Service Type
—
Point of Interconnection
Coxsackie 13.8kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Obtain a complete list of Hecate Energy's operating assets, including in-service dates, to accurately identify plants added since 2023.
Structured data lookup for Hecate Energy with rankings and aggregations.
Hecate Grid Gwent Storage 1
Data-driven briefing on Hecate Energy — fleet, generation, financial, and news signals.
KCE NY 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
KCE NY 31
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.