Riverhead Solar 2
36 MW generation in Suffolk, NY · In queue since February 2016 · Proposed COD January 2027
36 MW
Capacity
1
Components
Solar
10y 5m
In Queue
Facility Study
IA Phase
Signed Feb 2021
Queue → IA
5 years
IA → COD
5y 11m
Total Duration
5 years
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-01-01
Riverhead Solar 2 is a proposed 36 MW solar generation project located in Suffolk County, New York. The project, developed by Riverhead Solar 2, LLC, is in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-535, with a queue entry date of February 23, 2016. The proposed commercial operation date is January 1, 2027. The project's interconnection status is currently in the Facility Study phase.
The proposed project will interconnect to the LIPA grid at the Edwards 138kV point of interconnection. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Suffolk
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Riverhead Solar 2, LLC
Utility
LIPA
Entity
NYISO
Service Type
—
Point of Interconnection
Edwards 138kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE K
- Hub Confidence
- HIGH
- POI Substation
- Edwards Ferry Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Riverhead Solar 2Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.