NYC Energy
79.9 MW storage in Kings, NY · In queue since December 2015 · Proposed COD June 2027
79.9 MW
Capacity
1
Components
Battery
10y 7m
In Queue
Facility Study
IA Phase
COD target: 2027
Total Duration
11y 6m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
NYC Energy LLC is proposing the NYC Energy project, a 79.9 MW battery storage development in Kings County, New York. The project is located within the NYISO region and interconnected to the ConEd utility grid at the Hudson Avenue East 138kV point of interconnection. It entered the NYISO interconnection queue as queue ID NYISO-522 on December 16, 2015, and has a proposed commercial operation date of June 1, 2027. The project's interconnection status is currently in the System Impact Study phase.
The NYC Energy project consists solely of battery storage, with a total capacity of 79.9 MW. The project has been mentioned in recent news coverage related to the energy industry.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Kings
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
NYC Energy LLC
Utility
ConEd
Entity
NYISO
Service Type
—
Point of Interconnection
Hudson Avenue East 138kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE J
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- BROOKLYN_NAVY_YARD
- POI Substation
- Hudson Avenue Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26