Canisteo Wind (NYISO-519) — Project Summary

Queue ID
NYISO-519
Capacity
290.7 MW
Technology
Wind
Status
active
Location
Steuben, NY
Region
NYISO
Developer
Canisteo Wind Energy LLC
IA Status
Facility Study

Canisteo Wind

NYISO-519BetaActiveWindNYISOLBNL

290.7 MW generation in Steuben, NY · In queue since November 2015 · Proposed COD December 2027

BA: NYISISO/RTO: NYISONERC: NPCCRC: NYIS

290.7 MW

Capacity

1

Components

Wind

10y 8m

In Queue

Facility Study

IA Phase

Signed Feb 2021

Interconnection

Queue → IA

5y 3m

IA → COD

6y 10m

Total Duration

5y 3m

Construction50%
Queue EntryNov 2, 2015

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection AgreementFeb 8, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2027-12-01

Cross-source intelligence
Beta
Low confidence·1 sources·as of 2026-06-01
Expected COD
2027-12-01
From queue filing
Developer
Invenergy
Filed as Canisteo Wind Energy LLC
Status
Active
Active — in Facility Study phase per LBNL, IA executed 2021, PPA with NYPA secured 2019
Financing
Unannounced
Key milestones
Financing closeFeb 5, 2019

20-year physical PPA secured with New York Power Authority

source
IA executedFeb 8, 2021Most recent

Interconnection Agreement executed with NYISO

source
Project lifecycle
as of 2019-02-05
PhaseIA executedHornell Evening Tribune · 2019-02-05
OperationalNoHornell Evening Tribune · 2019-02-05
TechnologyWindHornell Evening Tribune · 2019-02-05
DeveloperInvenergyHornell Evening Tribune · 2019-02-05
PPA offtakerNew York Power AuthorityHornell Evening Tribune · 2019-02-05
About

The Canisteo Wind project is a proposed wind energy generation project located in Steuben County, New York. The project, developed by Canisteo Wind Energy LLC, has a total capacity of 289.8 MW. It is interconnected to the New York Independent System Operator (NYISO) queue under queue ID NYISO-519, with an entry date of November 2, 2015. The proposed commercial operation date is December 1, 2027, and its interconnection status is currently in the Facility Study phase.

The proposed project is linked to the existing Canisteo Wind Farm (EIA plant ID 62947). The project has been the subject of recent news coverage.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

NY

County

Steuben

Grid Region

NYISO (New York)

Market

ISO/RTO Member

Developer

Canisteo Wind Energy LLC

Utility

NYSEG

Entity

NYISO

Service Type

Point of Interconnection

Bennett 115kV

Data Source

LBNL

DeveloperInvenergyHornell Evening Tribune · 2019-02-05
TransactionPPAHornell Evening Tribune · 2019-02-05
OfftakerNew York Power AuthorityHornell Evening Tribune · 2019-02-05
PPA structurePhysicalHornell Evening Tribune · 2019-02-05
PPA term20 yearsHornell Evening Tribune · 2019-02-05
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
NYISO
Trading Hub
ZONE B
Hub Confidence
HIGH
Nearest Node (Estimated)
DUNKIRK__115KV_TB_200
POI Substation
Bennett Road Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (2)Beta

Last updated 2026-03-26

View all articles

No Ask reports yet for this entity.

Ask about Canisteo Wind
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.