Kenwood Tech Center
180 MW generation in Albany, NY · In queue since November 2025
180 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
Total Duration
8 months
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Project entered NYISO interconnection queue
The Kenwood Tech Center is a proposed 180 MW generation project located in Albany County, New York. The project, developed by EKG Group LLC, is interconnected to National Grid via the Albany?Bethlehem 115 kV Line #18. It is listed in the NYISO interconnection queue as entry NYISO-1754, with a queue entry date of November 11, 2025. The project's technology is listed as "Other" with a detail of "L," and its interconnection status is currently active.
The proposed project is listed in the NYISO interconnection queue, but no proposed commercial operation date or Interconnection Agreement (IA) status is available in the provided data. The project has appeared in recent news.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Albany
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
EKG Group LLC
Utility
National Grid
Entity
NYISO
Service Type
—
Point of Interconnection
Albany?Bethlehem 115 kV Line #18
Data Source
Live · NYISO
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Kenwood Tech CenterForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.