1 Gig Data Center East Fishkill, NY
1,000 MW generation in Dutchess, NY · In queue since July 2025
1,000 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
Total Duration
1 year
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Interconnection request filed with NYISO for 1000 MW data center load
The 1 Gig Data Center East Fishkill, NY project is a proposed 1,000 MW generation project located in Dutchess County, New York. Developed by Donovan Drive Holdings LLC, the project is interconnected to the Consolidated Edison (CONED) grid and has requested interconnection via queue position NYISO-1738 in the New York Independent System Operator (NYISO) queue on July 17, 2025. The project's technology is listed as "Other" with a detail of "L".
The proposed project is currently listed as "active" in the NYISO interconnection queue. The point of interconnection (POI) is the East Fishkill to Wood Street 345 kV lines (38 and 39).
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Dutchess
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Donovan Drive Holdings LLC
Utility
CONED
Entity
NYISO
Service Type
—
Point of Interconnection
East Fishkill to Wood Street 345 kV lines (38 and 39)
Data Source
Live · NYISO
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE G
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about 1 Gig Data Center East Fishkill, NYForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.