90 MW generation in Seneca, NY · In queue since May 2021 · Proposed COD September 2027
90 MW
Capacity
1
Components
Solar
5y 2m
In Queue
System Impact Study
IA Phase
COD target: 2027
Total Duration
6y 4m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-01
The North Seneca Solar Project, LLC is a proposed 105 MW solar generation project located in Seneca County, New York. The project, developed by North Seneca Solar Project, entered the NYISO interconnection queue on May 27, 2021, under queue ID NYISO-1188. Its proposed commercial operation date is September 1, 2027. The project's interconnection status is currently in the System Impact Study phase.
The proposed project is interconnected to the Hooks Road - Elbridge 115kV line#7. Recent news coverage indicates ongoing development of the project.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Seneca
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
North Seneca Solar Project
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Hooks Road - Elbridge 115kV line#7
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE B
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about North Seneca Solar Project, LLCForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.