KCE NY 29
79 MW storage in Suffolk, NY · In queue since December 2020 · Proposed COD December 2027
79 MW
Capacity
1
Components
Battery
5y 7m
In Queue
Facility Study
IA Phase
COD target: 2027
Total Duration
7 years
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
KCE NY 29 is a proposed 150 MW battery storage project located in Suffolk County, New York. The developer is KCE NY 29, LLC, and the interconnecting utility is LIPA. The project is currently active in the NYISO interconnection queue as entry NYISO-1123, with a queue entry date of December 14, 2020, and a proposed commercial operation date of October 1, 2027.
The point of interconnection for the project is the Kings 138 kV substation. The project consists solely of battery storage, with a total capacity of 150 MW.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Suffolk
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
KCE NY 29, LLC
Utility
LIPA
Entity
NYISO
Service Type
—
Point of Interconnection
Kings 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE K
- Hub Confidence
- HIGH
- POI Substation
- Kings Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about KCE NY 29Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.