East Fishkill
205 MW storage in Dutchess, NY · In queue since December 2020 · Proposed COD December 2029
205 MW
Capacity
1
Components
Battery
5y 11m
In Queue
System Impact Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
9 years
Interconnection request submitted to ISO/RTO
Interconnection Queue; status 11
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Sep 30, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered NYISO queue for System Impact Study
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of December 2029. No independent news or press releases found to validate or contradict this target date.
Developer: No news coverage or corporate announcements found to identify a parent company or operating entity behind the project LLC. Developer remains as filed in LBNL queue.
Status: LBNL shows active queue status in System Impact Study phase. No news coverage found to indicate project advancement, financing, or withdrawal.
About
Generated Apr 10, 2026 · Predates Sep 30, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The East Fishkill project is a proposed 205 MW battery storage development in Dutchess County, New York. Developed by Microgrid Networks, LLC, the project consists of 205 MW of battery capacity. It is currently active in the NYISO interconnection queue as entry NYISO-1122, with a queue entry date of December 11, 2020. The proposed commercial operation date is November 1, 2028, and the project's interconnection status is currently in the System Impact Study phase.
The proposed project would interconnect to the Central Hudson Gas & Electric (CHG&E) grid at the Shenandoah 115kV point of interconnection. The East Fishkill project has been mentioned in recent industry news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- NYISO queue source as of: Sep 30, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Dutchess
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
East Fishkill Storage 1, LLC
Utility
CHG&E
Entity
NYISO
Service Type
—
Point of Interconnection
Shenandoah 115kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE G
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- E_FISHKILL___LBMP
- POI Substation
- Shenandoah
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesKCE NY 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
KCE NY 31
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
KCE NY 21
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
KCE NY 30
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.