Flat Creek Solar
100 MW generation in Montgomery, NY · In queue since November 2020 · Proposed COD November 2028
100 MW
Capacity
1
Components
Solar
5y 6m
In Queue
System Impact Study
IA Phase
COD target: 2028
Total Duration
8 years
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-01
Flat Creek Solar 2 is a proposed 100 MW solar generation project located in Montgomery County, New York. The project, being developed by SED NY Holdings LLC, consists of 100 MW of solar photovoltaic generation. It is interconnected to the NYISO grid under queue ID NYISO-1115, with an interconnection queue entry date of November 23, 2020. The proposed commercial operation date is November 1, 2028, and the project's interconnection status is currently in the System Impact Study phase.
The proposed project is connected to the Edic - Princetown 345 kV Line# 352 and has been featured in recent news coverage related to development and industry trends. The interconnecting utility is NYPA.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Montgomery
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Flat Creek Solar NY LLC
Utility
NYPA
Entity
NYISO
Service Type
—
Point of Interconnection
Edic - Princetown 345 kV Line# 352
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo Ask reports yet for this entity.
Ask about Flat Creek SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.