Mill Point Solar
250 MW hybrid in Montgomery, NY · In queue since June 2020 · Proposed COD December 2028
250 MW
Capacity
1
Components
Solar
6y 1m
In Queue
System Impact Study
IA Phase
COD target: 2028
Total Duration
8y 6m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
- —·ConnectGen→Repsolsource
NY Office of Renewable Energy Siting approved project permits; Montgomery County filed legal challenge
sourceMill Point Solar is a proposed 250 MW hybrid solar and battery project located in Montgomery County, New York. Developed by ConnectGen Montgomery County LLC, the project consists of 250 MW of solar generation. It is currently active in the New York Independent System Operator (NYISO) interconnection queue as queue ID NYISO-1031, with an interconnection queue entry date of June 18, 2020. The proposed commercial operation date is December 1, 2028, and the project's interconnection status is currently in the System Impact Study phase.
The proposed project interconnects to the Marcy - New Scotland 345kV point of interconnection. Mill Point Solar has been the subject of recent news coverage, with six articles categorized as regulatory and industry news.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Montgomery
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
ConnectGen Montgomery County LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Marcy - New Scotland 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo Ask reports yet for this entity.
Ask about Mill Point SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.