SunEast Flat Stone Solar LLC
20 MW generation in Oneida, NY · In queue since March 2020 · Proposed COD November 2026
20 MW
Capacity
1
Components
Solar
6y 4m
In Queue
Facility Study
IA Phase
COD target: 2026
Total Duration
6y 8m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-11-01
The SunEast Flat Stone Solar LLC is a proposed solar generation project located in Oneida County, New York. The project, with a total capacity of 20 MW, is being developed by SED NY Holdings LLC. It is currently listed as active in the New York Independent System Operator (NYISO) interconnection queue under queue ID NYISO-1000.
The project entered the NYISO queue on March 18, 2020, and has a proposed commercial operation date of November 1, 2026. Its interconnection status is currently in the Facility Study phase. The point of interconnection is the Oneida - Rome 115kV line.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Oneida
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
SED NY Holdings LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Oneida - Rome 115kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about SunEast Flat Stone Solar LLCForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.