Scriba-Volney Series Reactor
— generation in Oswego, NY · In queue since August 2019
—
Capacity
0
Components
7y 2m
In Queue
—
IA Status
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Scriba-Volney Series Reactor is a proposed development project in Oswego County, New York, listed in the New York Independent System Operator (NYISO) interconnection queue under queue ID NYISO-0899. The project is being developed by Sithe/Independence Power Partners, LP. Although it is classified as a generation project, its technology is listed as "Other," with an alternating current (AC) technology designation. As its name indicates, the project involves a series reactor. No nameplate capacity is specified in the available queue data.
The project entered the NYISO queue on August 2, 2019, and its status is currently active. Its proposed point of interconnection is the Volney–Scriba 345 kV transmission line, with NM-NG (National Grid) identified as the associated transmission owner. The available data does not specify a proposed commercial operation date or the status of an interconnection agreement. The project is not linked to an existing operating plant in EIA records, and no recent news coverage is noted.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Oswego
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Sithe/Independence Power Partners, LP
Utility
Transmission Owner NM-NG Transmission Owner NaN Name: 51, dtype: object
Entity
NYISO
Service Type
—
Point of Interconnection
Volney - Scriba 345 kV
Data Source
Live · NYISO
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Scriba-Volney Series ReactorForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.