NWMT-432
50 MW hybrid in Wheatland, MT · In queue since September 2022 · Proposed COD September 2025
50 MW
Capacity
1
Components
Solar
3y 10m
In Queue
Facility Study
IA Phase
COD target: 2025
Total Duration
3 years
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-09-01
NWMT-432 is a proposed 50 MW solar and battery hybrid project located in Wheatland County, Montana. The project, which appeared in the NorthWestern Energy (NWMT) interconnection queue on September 6, 2022, consists of 50 MW of solar capacity. Its proposed commercial operation date is September 1, 2025.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 230 kV line between Harlowton and Judith Gap.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MT
County
Wheatland
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
ERIS
Point of Interconnection
230 kV line between Harlowton and Judith Gap
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project NWMT-432Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.