NWMT-335
80 MW hybrid in Wheatland, MT · In queue since September 2017 · Proposed COD October 2024
80 MW
Capacity
1
Components
Wind
8y 10m
In Queue
Facility Study
IA Phase
COD target: 2024
Total Duration
7y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-31
The proposed NWMT-335 project is an 80 MW hybrid wind and battery energy storage development in Wheatland County, Montana. Interconnection is requested with NorthWestern Energy via the NWMT queue, with an initial queue entry date of September 25, 2017. The project consists of 80 MW of wind generation capacity.
The proposed commercial operation date is October 31, 2024. The project's interconnection status is currently in the Facility Study phase, but is listed as suspended in the interconnection queue. The point of interconnection is the 230kV line from Judith Gap Auto to Judith Gap South.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MT
County
Wheatland
Grid Region
Mountain West
Market
—
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Service Type
NRIS
Point of Interconnection
230kV Line from Judith Gap Auto to Judith Gap South
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project NWMT-335Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.