NVE-Company LU
700 MW hybrid in Mineral, NV · In queue since September 2021 · Proposed COD December 2029
700 MW
Capacity
1
Components
Solar
4y 10m
In Queue
IA Executed
IA Phase
COD target: 2029
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2029-12-31
The proposed NVE-Company LU project is a 700 MW hybrid solar and battery energy storage development in Mineral County, Nevada. The project consists of 700 MW of solar photovoltaic generation.
The project is in the NV Energy interconnection queue, with an entry date of September 28, 2021. Its proposed commercial operation date is December 31, 2029, and the interconnection agreement has been executed. The developer is NVE.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NV
County
Mineral
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
NRIS
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.