NVE-Company KO
4.8 MW generation in Lyon, NV · In queue since September 2020 · Proposed COD October 2027
4.8 MW
Capacity
1
Components
Geothermal
5y 10m
In Queue
IA Executed
IA Phase
COD target: 2027
Total Duration
7y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2027-10-01
The NVE-Company KO development project is a proposed 4.8 MW geothermal generation facility located in Lyon County, Nevada. The project, developed by NVE, is interconnected with NV Energy and entered the utility's interconnection queue on September 17, 2020. The current proposed commercial operation date is October 1, 2027, and the interconnection agreement has been executed.
The project consists of a single 4.8 MW geothermal component. It is currently listed as an active project in the NV Energy interconnection queue.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NV
County
Lyon
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
NRIS
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project NVE-Company KOForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.