Project NVE-Company IH — Project Summary

Queue ID
NVE-Company IH
Capacity
80 MW
Technology
Solar
Status
active
Location
Pershing, NV
Region
West
Developer
IA Status
IA Executed

NVE-Company IH

NVE-Company IHBetaActiveSolarNVELBNL

80 MW generation in Pershing, NV · In queue since March 2018 · Proposed COD June 2021

BA: NEVPNERC: WECCRC: SPPW

80 MW

Capacity

1

Components

Solar

8y 4m

In Queue

IA Executed

IA Phase

COD target: 2021

Interconnection

Total Duration

3y 3m

Schedule

62 months past proposed COD

Construction75%
Queue EntryMar 19, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2021-06-01

About

The NVE-Company IH development project is an 80 MW solar generation project proposed in Pershing County, Nevada. The project is located in the West region and is being developed within the NV Energy (NVE) utility territory. It entered the NV Energy interconnection queue on March 19, 2018, and has a proposed commercial operation date of June 1, 2021.

The project's interconnection agreement (IA) has been executed. The project has appeared in recent news.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

NV

County

Pershing

Grid Region

Mountain West

Market

Developer

Utility

NV Energy

Entity

NVE

Service Type

NRIS/ERIS

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Project NVE-Company IH
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.