NVE-Company IF
350 MW generation in Humboldt, NV · In queue since March 2018 · Proposed COD February 2026
350 MW
Capacity
1
Components
Solar
8y 4m
In Queue
IA Executed
IA Phase
COD target: 2026
Total Duration
7y 11m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-02-01
The NVE-Company IF development project is a proposed 350 MW solar generation facility located in Humboldt County, Nevada. The project is sponsored by NV Energy and is currently active in the NV Energy interconnection queue, with an entry date of March 19, 2018. The project has an executed Interconnection Agreement (IA) and a proposed commercial operation date of February 1, 2026.
The project consists of 350 MW of solar photovoltaic generation capacity. The project has appeared in recent news coverage regarding NV Energy's renewable energy development plans.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NV
County
Humboldt
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
NRIS
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project NVE-Company IFForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.