Project NVE-25-00432 — Project Summary

Queue ID
NVE-25-00432
Capacity
900 MW
Technology
Solar+Battery
Status
active
Location
Lyon, NV
Region
West
Developer
—
IA Status
In Progress (unknown study)

NVE-25-00432

NVE-25-00432BetaActiveSolarBatteryNVELBNL

900 MW hybrid in Lyon, NV · In queue since July 2025 · Proposed COD September 2029

BA: NEVPNERC: WECCRC: SPPW

900 MW

Capacity

1

Components

Solar

1y 4m

In Queue

In Progress (unknown study)

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

4 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 2m

In Study38%
Queue EntryJul 30, 2025

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-09-01

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Queue ID NVE-25-00432 is a proposed hybrid solar and battery storage development project in Lyon County, Nevada, in the western United States. The project has a total capacity of 900 megawatts (MW). The queue data lists both solar and battery technologies, but only the solar component's capacity, 900 MW, is itemized. The developer is not identified in the available records.

The project is in the interconnection queue administered by NV Energy, the utility serving the area. It entered the queue on July 30, 2025, and has a proposed commercial operation date of September 1, 2029. The project remains active, and its interconnection agreement status is listed as in progress, although the specific study phase is not identified. The requested service type is Network Resource Interconnection Service and Energy Resource Interconnection Service (NRIS/ERIS).

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

NV

County

Lyon

Grid Region

Mountain West

Market

—

Developer

—

Utility

NV Energy

Entity

NVE

Service Type

NRIS/ERIS

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.