MPC-MPC04000
300 MW generation in Oliver, ND · In queue since April 2019 · Proposed COD December 2023
300 MW
Capacity
1
Components
Wind
7y 3m
In Queue
IA Executed
IA Phase
COD target: 2023
Total Duration
4y 8m
Schedule
32 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2023-12-01
MPC-MPC04000 is a proposed 300 MW wind generation project located in Oliver County, North Dakota. The project is being developed by Minnkota Power Cooperative (MPC) and is listed in the Midcontinent Independent System Operator (MISO) interconnection queue. The project entered the queue on April 25, 2019, with a proposed commercial operation date of December 1, 2023. Its interconnection status is currently in the Facility Study phase, and the point of interconnection is the Square Butte 230 kV Substation.
The proposed project consists of 300 MW of wind generation capacity. It is currently listed as an active project within the MISO queue.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ND
County
Oliver
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
Minnkota Power Cooperative
Entity
MPC
Service Type
NRIS
Point of Interconnection
Square Butte 230 kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.