MPC-MPC03700
130 MW generation in Richland, ND · In queue since May 2018 · Proposed COD April 2027
130 MW
Capacity
1
Components
Solar
8y 2m
In Queue
IA Executed
IA Phase
COD target: 2027
Total Duration
8y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-04-13
MPC-MPC03700 is a proposed 130 MW solar generation project located in Richland County, North Dakota. The project is being developed by Minnkota Power Cooperative (MPC) and interconnected within the Midcontinent Independent System Operator (MISO) queue. The project entered the queue on May 4, 2018, and has a proposed commercial operation date of April 13, 2027. The interconnection agreement (IA) for the project has been executed. The point of interconnection (POI) is the Frontier-Wahpeton 230 kV Line.
The proposed project consists of 130 MW of solar photovoltaic generation capacity. It is currently listed as an active project within the MISO interconnection queue. The project has appeared in recent news coverage regarding renewable energy development in the region.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ND
County
Richland
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
Minnkota Power Cooperative
Entity
MPC
Service Type
ERIS
Point of Interconnection
Frontier-Wahpeton 230 kV Line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MPC-MPC03700Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.