Surplus; J944
200 MW storage in New Madrid, MO · In queue since August 2025 · Proposed COD June 2028
200 MW
Capacity
1
Components
Battery
9 months
In Queue
—
IA Status
COD target: 2028
Total Duration
2y 10m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
MISO-S1117 is a proposed 200 MW battery storage project located in New Madrid County, Missouri. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of August 31, 2025. Entergy Arkansas, LLC is the utility associated with the project.
The proposed project is currently in active status within the MISO queue, undergoing a System Impact Study (SIS). The point of interconnection (POI) is the Marston 161 kV substation.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MO
County
New Madrid
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
Marston 161 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Mauston
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Surplus; J944Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.