Surplus
100 MW storage in Fayette, IL · In queue since July 2025 · Proposed COD June 2026
100 MW
Capacity
1
Components
Battery
1y 4m
In Queue
—
IA Status
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
11 months
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-30
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 25, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered MISO queue as active project
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of June 2026. No independent news or research sources found to validate or contradict this date.
Developer: LBNL filing shows no developer information. No press releases, news articles, or corporate announcements found identifying the project sponsor or operating company.
Status: LBNL queue status shows active as of July 2025. Absence of news coverage suggests early-stage development with no major milestones publicly announced.
About
Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
MISO-S1104 is a proposed 100 MW battery storage project located in Fayette County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on July 28, 2025. Ameren Illinois is the utility associated with the project.
The project's service type is System Impact Study (SIS), and its status in the MISO queue is currently active.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- MISO queue source as of: Oct 25, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Fayette
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Ramsey
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Ramsey Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.