Surplus
150 MW storage in St. Clair, IL · In queue since January 2025 · Proposed COD September 2029
150 MW
Capacity
1
Components
Battery
1y 4m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-01
MISO-S1077 is a proposed 150 MW battery storage project located in St. Clair County, Illinois. The project is in the MISO interconnection queue, having entered on January 13, 2025. Ameren Illinois is the utility associated with the project, which is currently listed as active in the queue. The point of interconnection is Fayetteville Bee Hollow Road, and the service type is SIS (System Impact Study).
The development project is sponsored by an unknown developer. It is designed as a standalone storage facility, utilizing battery storage technology. The project has appeared in recent news coverage regarding energy storage development in the region.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
St. Clair
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Fayetteville Bee Hollow Road
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about SurplusForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.