Surplus; J1450
150 MW hybrid in Webster, KY · In queue since February 2025 · Proposed COD August 2026
150 MW
Capacity
1
Components
Other
1y 3m
In Queue
—
IA Status
COD target: 2026
Total Duration
1y 6m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-08-31
MISO-S1073 is a proposed 150 MW generation project located in Webster County, Kentucky. The project, listed under the utility BIG RIVERS ELECTRIC CORPORATION, entered the MISO interconnection queue on February 19, 2025. The point of interconnection is the Hopkins to Reid EVH 161kV line.
The project's interconnection service type is System Impact Study (SIS), and its status is currently listed as active within the MISO queue. The technology type is categorized as "Other".
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
KY
County
Webster
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
BIG RIVERS ELECTRIC CORPORATION
Entity
MISO
Service Type
—
Point of Interconnection
Hopkins to Reid EVH 161kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Surplus; J1450Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.