Surplus; Pine River Solar
80 MW hybrid in Gratiot, MI · In queue since April 2022 · Proposed COD September 2023
80 MW
Capacity
1
Components
Solar
4y 6m
In Queue
IA Executed
IA Phase
Signed May 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1 month
IA → COD
1y 4m
Total Duration
1 month
Schedule
38 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done
Project under construction
Typical: 12–24 months
Proposed COD: 2023-09-01
Surplus; Pine River Solar (queue ID MISO-S1021) is a proposed solar development project located in Gratiot County, Michigan, within the Midcontinent Independent System Operator (MISO) region. The project has a total capacity of 80 MW and is classified as a hybrid project. Its technology details list both solar and "other" components, though the only component with a specified capacity is 80 MW of solar. The transmission owner is the Michigan Electric Transmission Company (METC), and the project's point of interconnection is the Luce Substation.
The project entered the MISO interconnection queue on April 25, 2022, as a surplus interconnection request, and its queue status is active. An interconnection agreement (IA) was executed on May 17, 2022. The proposed commercial operation date was September 1, 2023. The project is linked to an existing operating plant in U.S. Energy Information Administration (EIA) records, the Pine River Solar Park (EIA plant ID 67941), with a match confidence of 0.81.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MI
County
Gratiot
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Luce Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CONS.PNRVR.SOL
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Surplus; Pine River SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.