Surplus; J947
100 MW hybrid in — · In queue since April 2022 · Proposed COD June 2023
100 MW
Capacity
1
Components
Other
4y 6m
In Queue
—
IA Status
COD target: 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
1y 2m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-06-01
MISO-S1017, listed in the queue under the name "Surplus; J947," is a proposed battery storage development project in the Midcontinent Independent System Operator (MISO) region. The project is classified as a hybrid, with technology details listing both "Other" and battery components. Its total capacity is 100 MW, all of which is recorded under a single component designated "Other." The project would interconnect at the Tennyson 138kV point of interconnection, within the transmission system of American Transmission Company. The data does not identify the county, state, or developer.
The proposed project entered the MISO interconnection queue on April 11, 2022, and currently holds an active status. Its proposed commercial operation date was June 1, 2023. The "Surplus" designation in its name suggests a surplus interconnection service request, a mechanism that allows additional generation or storage to use unused capacity at an existing interconnection point. The available data does not specify the status of an interconnection agreement for the project.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
—
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Tennyson 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Hub Confidence
- UNKNOWN
- Nearest Node (Estimated)
- ALTE.GRANTCTY
- POI Substation
- Tennyson
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Surplus; J947Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.