Surplus; J878
60 MW hybrid in — · In queue since April 2021
60 MW
Capacity
1
Components
Other
5y 6m
In Queue
—
IA Status
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed project designated "Surplus; J878" (queue ID MISO-S1005) is a hybrid battery storage development project in the interconnection queue of the Midcontinent Independent System Operator (MISO). It has a total proposed capacity of 60 megawatts (MW). The project's technology is listed as Battery, with technology details identifying both "Other" and "Battery" elements. Its single reported component is categorized as "Other" and accounts for the full 60 MW. The available data do not identify the project's county, state, or developer.
The project entered the MISO interconnection queue on April 2, 2021, and its queue status is currently listed as active. The "Surplus" designation in the project name suggests it may be a surplus interconnection request associated with queue position J878, though the data do not explicitly confirm this. No proposed commercial operation date or interconnection agreement status has been reported. The project is not linked to an existing operating plant in EIA records, and no recent news coverage of it has been identified.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
—
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Surplus; J878Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.