Replacing 160 MW of Solar with 80 MW of Solar and 90 MW of BESS; Bell Solar (MISO-R5063) — Project Summary

Queue ID
MISO-R5063
Capacity
170 MW
Technology
Solar+Battery
Status
active
Location
Shiawassee, MI
Region
MISO
Developer
—
IA Status
—

Replacing 160 MW of Solar with 80 MW of Solar and 90 MW of BESS; Bell Solar

MISO-R5063BetaActiveSolarBatteryMISOLBNL + Live

170 MW hybrid in Shiawassee, MI · In queue since May 2025

BA: MISOISO/RTO: MISONERC: RFCRC: MISO

170 MW

Capacity

1

Components

Solar

1y 6m

In Queue

—

IA Status

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

1y 6m

Pre-Study0%
Queue EntryMay 9, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 25, 2026 queue source. See the queue record for reported project facts.

Research COD
—
Developer in saved assessment
—
Status at research time
Active
Active — queue modification request filed May 2025 to replace solar-only with hybrid solar+storage configuration
Financing
Not recorded

Milestones in this assessment

IA executedMay 2025Latest in this assessment

Queue modification request submitted to MISO to reconfigure Bell Solar from 160 MW solar to 80 MW solar + 90 MW BESS

Research sources and reasoning (0 recorded sources)

low confidence at research time

No source list recorded with this assessment.

Commercial operation date: No COD information available in LBNL snapshot or search results. Project entered MISO queue May 2025 as a modification request (replacing 160 MW solar with 80 MW solar + 90 MW BESS).

Developer: No developer identified in LBNL filing or search results. Project name indicates a reconfiguration of existing Bell Solar project but no entity attribution found.

Status: LBNL status shows active queue position. Project represents a capacity modification (downsizing solar from 160 MW to 80 MW while adding 90 MW BESS) rather than a new greenfield development.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

MISO-R5063 is a proposed 170 MW hybrid generation project located in Shiawassee County, Michigan. The project, which is in the MISO interconnection queue, entered the queue on May 9, 2025. The interconnecting utility is METC.

The project's technology is listed as "Other" with a detail of "Hybrid," suggesting a combination of generation and/or storage technologies. The project is currently listed as "active" in the interconnection queue.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • MISO queue source as of: Oct 25, 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

MI

County

Shiawassee

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

—

Utility

METC

Entity

MISO

Service Type

—

Point of Interconnection

BELL ROAD - CORNELL 138.0kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MICHIGAN.HUB
Hub Confidence
HIGH
POI Substation
Cornell

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.