MISO-R5063
170 MW generation in Shiawassee, MI · In queue since May 2025
170 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
Total Duration
1 year
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
MISO-R5063 is a proposed 170 MW hybrid generation project located in Shiawassee County, Michigan. The project, which is in the MISO interconnection queue, entered the queue on May 9, 2025. The interconnecting utility is METC.
The project's technology is listed as "Other" with a detail of "Hybrid," suggesting a combination of generation and/or storage technologies. The project is currently listed as "active" in the interconnection queue.
Generated from interconnection queue and public data sources
State
MI
County
Shiawassee
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
BELL ROAD - CORNELL 138.0kV
Data Source
Live · MISO
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-R5063Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.