MISO-R1030
— generation in — · In queue since January 2023 · Proposed COD October 2024
—
Capacity
0
Components
3y 9m
In Queue
—
IA Status
COD target: 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
1y 9m
Schedule
25 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-01
MISO-R1030 is a proposed generation project listed in the interconnection queue of the Midcontinent Independent System Operator (MISO). The project's technology is classified as "Other" in the queue data, and no developer, capacity figure, or county and state location is specified in the available records. The proposed point of interconnection is the Slocum substation, identified as PSSE Bus #264511.
The project entered the MISO interconnection queue on January 5, 2023, and its status is listed as active. It had a proposed commercial operation date of October 1, 2024. That date has passed while the project remains active in the queue, suggesting the original timeline has not been met. No information on the status of an interconnection agreement is provided, and the project is not linked to an existing operating plant in EIA records.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
—
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Slocum (PSSE Bus #264511)
Data Source
Live · MISO
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-R1030Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.