Replacing 30 MW of existing coal generation with BESS at Burlington Generation Station; Burlington 5
212 MW hybrid in Des Moines, IA · In queue since February 2022 · Proposed COD December 2024
212 MW
Capacity
1
Components
Other
4y 8m
In Queue
—
IA Status
COD target: 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 10m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
The proposed project "Replacing 30 MW of existing coal generation with BESS at Burlington Generation Station; Burlington 5" is a battery-based development project in Des Moines County, Iowa. Listed in the Midcontinent Independent System Operator (MISO) interconnection queue under ID MISO-R1019, it is classified as a hybrid project with a total capacity of 212 MW. Its technology is recorded as both "Other" and "Battery," and the only itemized component is a 212 MW "Other" entry. As its name indicates, the project involves a battery energy storage system (BESS) intended to replace 30 MW of existing coal generation at the Burlington Generation Station. The associated utility is Alliant Energy West.
The project entered the MISO queue on February 15, 2022, and its status is listed as active. It proposes to connect at the Burlington 161kV point of interconnection and has requested Network Resource Interconnection Service (NRIS). The proposed commercial operation date was December 31, 2024. The provided data does not specify the status of an interconnection agreement.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IA
County
Des Moines
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
Alliant Energy West
Entity
MISO
Service Type
NRIS
Point of Interconnection
Burlington 161kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Burlington Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Replacing 30 MW of existing coal generation with BESS at Burlington Generation Station; Burlington 5Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.