Replace Hoot Lake units 2 and 3 (144.8 MW) with Seventeen (17) Sungrow 3 MW solar inverters and PV panels at 49.9 MW; Hoot Lake 2 & 3 (MISO-R1001) — Project Summary

Queue ID
MISO-R1001
Capacity
49.9 MW
Technology
Solar
Status
active
Location
Otter Tail, MN
Region
MISO
Developer
—
IA Status
—

Replace Hoot Lake units 2 and 3 (144.8 MW) with Seventeen (17) Sungrow 3 MW solar inverters and PV panels at 49.9 MW; Hoot Lake 2 & 3

MISO-R1001BetaActiveSolarOtherMISOLBNL + Live

49.9 MW hybrid in Otter Tail, MN · In queue since May 2020 · Proposed COD April 2022

BA: MISOISO/RTO: MISONERC: MRORC: MISO

49.9 MW

Capacity

1

Components

Solar

6y 5m

In Queue

—

IA Status

COD target: 2022

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

4 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

1y 11m

Schedule

55 months past proposed COD

Pre-Study0%
Queue EntryMay 15, 2020

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-04-15

About

MISO-R1001, listed in the queue as "Hoot Lake 2 & 3," is a proposed 49.9 MW solar development project in Otter Tail County, Minnesota. The project would replace Hoot Lake units 2 and 3, which have a combined capacity of 144.8 MW, with photovoltaic panels and seventeen Sungrow 3 MW solar inverters. Although it is classified as a hybrid project, with technology types listed as solar and "other," its only specified component is 49.9 MW of solar capacity. The associated utility is Otter Tail Power Company.

The project entered the Midcontinent Independent System Operator (MISO) interconnection queue on May 15, 2020, and remains active. It has requested Network Resource Interconnection Service (NRIS) at the Hoot Lake 115 kV point of interconnection. Its proposed commercial operation date was April 15, 2022. The provided data does not include an interconnection agreement status. The project has been linked, with a match confidence of 0.92, to an existing operating plant in U.S. Energy Information Administration records, Hoot Lake Solar (EIA plant ID 65066).

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

MN

County

Otter Tail

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

—

Utility

OTTER TAIL POWER COMPANY

Entity

MISO

Service Type

NRIS

Point of Interconnection

Hoot Lake 115KV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MINN.HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
OTP.HLSOLAR

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.