Replace Hoot Lake units 2 and 3 (144.8 MW) with Seventeen (17) Sungrow 3 MW solar inverters and PV panels at 49.9 MW; Hoot Lake 2 & 3
49.9 MW hybrid in Otter Tail, MN · In queue since May 2020 · Proposed COD April 2022
49.9 MW
Capacity
1
Components
Solar
6y 5m
In Queue
—
IA Status
COD target: 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
1y 11m
Schedule
55 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-04-15
MISO-R1001, listed in the queue as "Hoot Lake 2 & 3," is a proposed 49.9 MW solar development project in Otter Tail County, Minnesota. The project would replace Hoot Lake units 2 and 3, which have a combined capacity of 144.8 MW, with photovoltaic panels and seventeen Sungrow 3 MW solar inverters. Although it is classified as a hybrid project, with technology types listed as solar and "other," its only specified component is 49.9 MW of solar capacity. The associated utility is Otter Tail Power Company.
The project entered the Midcontinent Independent System Operator (MISO) interconnection queue on May 15, 2020, and remains active. It has requested Network Resource Interconnection Service (NRIS) at the Hoot Lake 115 kV point of interconnection. Its proposed commercial operation date was April 15, 2022. The provided data does not include an interconnection agreement status. The project has been linked, with a match confidence of 0.92, to an existing operating plant in U.S. Energy Information Administration records, Hoot Lake Solar (EIA plant ID 65066).
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MN
County
Otter Tail
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
OTTER TAIL POWER COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
Hoot Lake 115KV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- OTP.HLSOLAR
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.