MISO-J986
149.76 MW generation in Wood, WI · In queue since March 2018 · Proposed COD September 2020
149.76 MW
Capacity
1
Components
Solar
8y 7m
In Queue
IA Executed
IA Phase
Signed May 2021
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 2m
Total Duration
3y 2m
Schedule
75 months past proposed COD
Study Phase
DPP-2018-APR East (ATC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 12–24 months
Proposed COD: 2020-09-01
MISO-J986 is a proposed solar generation project located in Wood County, Wisconsin, with a total capacity of 149.76 MW. The project consists of a single solar component and is situated within the service territory of American Transmission Co. (ATC). It is planned to connect to the grid at the Port Edwards – Sand Lake 138 kV point of interconnection. No developer or project name has been publicly identified in the queue data.
The project entered the Midcontinent Independent System Operator (MISO) interconnection queue on March 12, 2018. It was studied in the DPP-2018-APR East (ATC) cycle of MISO's Definitive Planning Phase and requested Network Resource Interconnection Service (NRIS). An interconnection agreement was executed on May 5, 2021. The project's proposed commercial operation date was September 1, 2020, which precedes the agreement's execution date. Its queue status remains active.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WI
County
Wood
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
American Transmission Co.
Entity
MISO
Service Type
NRIS
Point of Interconnection
Port Edwards - Sand Lake 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Port Edwards
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J986Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.