MISO-J963
9 MW generation in Cedar, IA · In queue since March 2018 · Proposed COD January 2017
9 MW
Capacity
1
Components
Diesel
8y 7m
In Queue
IA Executed
IA Phase
Signed Jun 2021
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 3m
Total Duration
3y 3m
Schedule
119 months past proposed COD
Study Phase
DPP-2018-APR West
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 12–36 months
Proposed COD: 2017-01-01
MISO-J963 is a proposed 9 MW diesel-fired generation project in Cedar County, Iowa, within the Midcontinent Independent System Operator (MISO) region. The interconnection queue classifies its technology as "Other," with a single diesel component accounting for the full 9 MW. The project would connect to the transmission system at the Bennett (CIPCO) – Graham 69 kV line tap, in the service territory of ITC Midwest. It has requested Network Resource Interconnection Service (NRIS). No developer name is listed in the available queue data.
The project entered the MISO interconnection queue on March 12, 2018, and was studied in the DPP-2018-APR West cycle of MISO's Definitive Planning Phase. Its listed proposed commercial operation date is January 1, 2017, which is earlier than its queue entry date. An interconnection agreement was executed on June 15, 2021, and the project's queue status remains active.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IA
County
Cedar
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Service Type
NRIS
Point of Interconnection
Bennett (CIPCO) - Graham 69 Kv Line Tap
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J963Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.