MISO-J874
150 MW generation in Murray, MN · In queue since June 2017 · Proposed COD September 2021
150 MW
Capacity
1
Components
Solar
9y 4m
In Queue
Construction
IA Phase
Signed May 2021
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 11m
IA → COD
4 months
Total Duration
3y 11m
Schedule
62 months past proposed COD
Study Phase
DPP-2017-AUG West
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Under Construction; GIA
Project under construction
Typical: 12–24 months
Proposed COD: 2021-09-30
MISO-J874 is a proposed 150 MW solar generation project located in Murray County, Minnesota. The development project is a standalone solar facility with no storage or other hybrid components. It is situated within the territory of Northern States Power Company, and its point of interconnection is the Fenton–Chanarambie 115 kV transmission line. No developer name is listed in the available queue data.
The project is in the interconnection queue of the Midcontinent Independent System Operator (MISO), which it entered on June 16, 2017. It was studied in the DPP-2017-AUG West cycle of MISO's Definitive Planning Phase and requested Network Resource Interconnection Service (NRIS). Its interconnection agreement was executed on May 19, 2021, and the agreement status is listed as "Construction." The proposed commercial operation date is September 30, 2021, and the project's queue status remains active.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MN
County
Murray
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
Fenton - Chanarambie 115kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J874Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.