MISO-J868
37.2 MW generation in Concordia Parish, LA · In queue since June 2017 · Proposed COD December 1990
37.2 MW
Capacity
1
Components
Other
9y 4m
In Queue
Construction
IA Phase
Signed Mar 2020
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 9m
Total Duration
2y 9m
Schedule
437 months past proposed COD
Study Phase
DPP-2017-AUG South
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Under Construction; GIA
Project under construction
Typical: 12–36 months
Proposed COD: 1990-12-03
MISO-J868 is a proposed 37.2 MW generation project located in Concordia Parish, Louisiana, within the Midcontinent Independent System Operator (MISO) region. The project is classified under the "Other" technology category and consists of a single 37.2 MW component. No developer is identified in the available data. The project's transmission owner is Entergy, and it is proposed to interconnect at the Plantation 115 kV Substation. It has requested Network Resource Interconnection Service (NRIS).
The project entered the MISO interconnection queue on June 16, 2017, and was studied in the DPP-2017-AUG South cycle. Its interconnection agreement status is listed as "Construction," with an agreement date of March 5, 2020. The queue record lists a proposed commercial operation date of December 3, 1990, which predates the queue entry date. The project's status in the queue remains active.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
LA
County
Concordia Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
Entergy
Entity
MISO
Service Type
NRIS
Point of Interconnection
Plantation 115 kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Plantation Road Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J868Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.