MISO-J866
200 MW generation in Tunica, MS · In queue since June 2017 · Proposed COD March 2020
200 MW
Capacity
1
Components
Wind
9y 4m
In Queue
Construction
IA Phase
Signed Apr 2020
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 10m
Total Duration
2y 10m
Schedule
80 months past proposed COD
Study Phase
DPP-2017-AUG South
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Under Construction; GIA
Project under construction
Typical: 18–36 months
Proposed COD: 2020-03-30
MISO-J866 is a proposed 200 MW wind generation project located in Tunica County, Mississippi, within the Midcontinent Independent System Operator (MISO) region. The project consists of a single wind component totaling 200 MW and is situated in the service territory of Entergy. No developer has been identified in the available data. The project would interconnect at the Batesville–Robert E. Ritchie 230 kV transmission line and has requested Network Resource Interconnection Service (NRIS).
The project entered the MISO interconnection queue on June 16, 2017, and was studied as part of the DPP-2017-AUG South study cycle. Its proposed commercial operation date was March 30, 2020. The project's interconnection agreement status is listed as "Construction," with an interconnection agreement date of April 6, 2020. As of the most recent data, the project remains active in the queue.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MS
County
Tunica
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
Entergy
Entity
MISO
Service Type
NRIS
Point of Interconnection
Batesville - Robert E. Ritchie 230 kV line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Batesville
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J866Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.