MISO-J844
300 MW generation in Knox, IL · In queue since June 2017 · Proposed COD September 2020
300 MW
Capacity
1
Components
Wind
9y 4m
In Queue
Construction
IA Phase
Signed Dec 2019
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 6m
IA → COD
9 months
Total Duration
2y 6m
Schedule
75 months past proposed COD
Study Phase
DPP-2017-AUG Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Under Construction; GIA
Project under construction
Typical: 18–36 months
Proposed COD: 2020-09-01
MISO-J844 is a proposed 300 MW wind generation project located in Knox County, Illinois. The development project is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO), with Ameren Transmission Company of Illinois as the transmission owner. The project would consist entirely of wind generation and is proposed to interconnect at the Sandburg Substation 138kV Bus. It has requested Energy Resource Interconnection Service (ERIS).
The project entered the MISO queue on June 16, 2017, and was studied in the DPP-2017-AUG Central cycle of MISO's Definitive Planning Phase. Its interconnection agreement was executed on December 10, 2019, and the agreement status is listed as "Construction." The project's proposed commercial operation date was September 1, 2020. As of the latest data, MISO-J844 remains in active status in the interconnection queue.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Knox
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Entity
MISO
Service Type
ERIS
Point of Interconnection
Sandburg Substation 138kV Bus
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J844Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.