MISO-J732
561.5 MW generation in Douglas, WI · In queue since June 2017 · Proposed COD June 2021
561.5 MW
Capacity
1
Components
Gas
9y 4m
In Queue
Construction
IA Phase
Signed Jul 2020
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 1m
IA → COD
11 months
Total Duration
3y 1m
Schedule
66 months past proposed COD
Study Phase
DPP-2017-AUG East (ATC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Under Construction; GIA
Project under construction
Typical: 24–48 months
Proposed COD: 2021-06-08
MISO-J732 is a proposed natural gas-fired generation project located in Douglas County, Wisconsin. The development project has a total capacity of 561.5 MW, consisting entirely of a single gas component. It is planned to interconnect at the Arrowhead – Stone Lake 345 kV Line within the service territory of American Transmission Co. (ATC). The project has requested Network Resource Interconnection Service (NRIS).
The project entered the Midcontinent Independent System Operator (MISO) interconnection queue on June 16, 2017. It was studied in the DPP-2017-AUG East (ATC) phase of MISO's Definitive Planning Phase process. An interconnection agreement was executed on July 29, 2020, and the agreement's status is listed as "Construction." The project's proposed commercial operation date was June 8, 2021. As of the latest available data, the project remains active in the MISO queue.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WI
County
Douglas
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
American Transmission Co.
Entity
MISO
Service Type
NRIS
Point of Interconnection
Arrowhead - Stone Lake 345kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J732Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.