MISO-J718
49.98 MW generation in Fillmore, MN · In queue since September 2016 · Proposed COD December 2020
49.98 MW
Capacity
1
Components
Solar
10y 1m
In Queue
Construction
IA Phase
Signed Apr 2020
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 7m
IA → COD
8 months
Total Duration
3y 7m
Schedule
71 months past proposed COD
Study Phase
DPP-2017-FEB West
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Under Construction; GIA
Project under construction
Typical: 12–24 months
Proposed COD: 2020-12-31
MISO-J718 is a proposed 49.98 MW solar generation project located in Fillmore County, Minnesota. The development project is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO), with Dairyland Power Cooperative identified as the interconnecting utility. The project would connect to the grid at the Cherry Grove 69kV Substation and has requested Network Resource Interconnection Service (NRIS). No developer or project name is identified in the available queue data.
The project entered the MISO interconnection queue on September 13, 2016, and was studied as part of the DPP-2017-FEB West study cycle. Its interconnection agreement was executed on April 21, 2020, and the agreement status is listed as "Construction." The project's proposed commercial operation date was December 31, 2020. As of the most recent queue data, the project retains an active status.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MN
County
Fillmore
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
DAIRYLAND POWER COOPERATIVE
Entity
MISO
Service Type
NRIS
Point of Interconnection
Cherry Grove 69kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J718Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.