Project MISO-J604 — Project Summary

Queue ID
MISO-J604
Capacity
99.96 MW
Technology
Solar
Status
active
Location
Sunflower, MS
Region
MISO
Developer
IA Status
IA Executed

MISO-J604

MISO-J604BetaActiveSolarMISOLBNL

99.96 MW generation in Sunflower, MS · In queue since May 2016 · Proposed COD September 2021

BA: MISOISO/RTO: MISONERC: SERCRC: MISO

99.96 MW

Capacity

1

Components

Solar

10y 2m

In Queue

IA Executed

IA Phase

Signed Jun 2018

Interconnection

Queue → IA

2y 1m

IA → COD

3y 3m

Total Duration

2y 1m

Schedule

59 months past proposed COD

Study Phase

DPP-2016-AUG South

Construction75%
Queue EntryMay 9, 2016

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection AgreementJun 12, 2018

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2021-09-15

About

The proposed MISO-J604 project is a 100 MW solar generation project located in Mississippi. The project was entered into the MISO interconnection queue on May 9, 2016, with a proposed commercial operation date of September 1, 2018. The interconnection agreement for the project has been executed.

The point of interconnection for the project is the Ruleville 115kV Substation. The project consists of 100 MW of solar photovoltaic generation.

Generated from interconnection queue and public data sources

Development Risk

Realization history for this asset — final cost vs plan, COD slip vs original date, and construction duration vs cohort. Retrospective context for the operating risk view above. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

Final cost vs plan
COD vs original date
Construction duration vs cohort
Project Details

State

MS

County

Sunflower

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

Entity

MISO

Service Type

Point of Interconnection

Ruleville 115kV Sub

Data Source

LBNL

Risk Analytics

Composite operating risk view for this asset — climate hazards across its remaining operating life, observed generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — 10-year P50 trajectory accounting for degradation, observed curtailment, and market conditions, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
Degradation-adjusted CF
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR bands, and refinancing risk for this asset — 10-year cashflow projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year cashflow horizon
P10 / P50 / P90 DSCR bands
Price + demand + policy scenarios
Market Context
Approximate
ISO / RTO
MISO
Trading Hub
LOUISIANA.HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
EMBA.SUNFLOWER
POI Substation
Ruleville Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Project MISO-J604
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.