MISO-J603
99.96 MW generation in Ashley, AR · In queue since May 2016 · Proposed COD September 2021
99.96 MW
Capacity
1
Components
Solar
10y 2m
In Queue
IA Executed
IA Phase
Signed Jun 2018
Queue → IA
2y 1m
IA → COD
3y 3m
Total Duration
2y 1m
Schedule
59 months past proposed COD
Study Phase
DPP-2016-AUG South
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2021-09-15
MISO-J603 is a proposed 100 MW solar generation project located in Arkansas. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue with an entry date of May 9, 2016. The proposed commercial operation date is September 1, 2018, and the Interconnection Agreement (IA) has been executed.
The point of interconnection (POI) is listed as a tap on the Montrose Mist 115 kV line. The project is currently listed as active in the MISO queue.
Generated from interconnection queue and public data sources
Realization history for this asset — final cost vs plan, COD slip vs original date, and construction duration vs cohort. Retrospective context for the operating risk view above. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
AR
County
Ashley
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Tap on Montrose – Mist 115 kV line
Data Source
LBNL
Composite operating risk view for this asset — climate hazards across its remaining operating life, observed generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — 10-year P50 trajectory accounting for degradation, observed curtailment, and market conditions, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this asset — 10-year cashflow projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J603Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.