MISO-J571
6.4 MW generation in Kalamazoo, MI · In queue since May 2016 · Proposed COD August 2018
6.4 MW
Capacity
1
Components
Gas
10y 2m
In Queue
IA Executed
IA Phase
Signed Aug 2018
Queue → IA
2y 3m
IA → COD
<1 month
Total Duration
2y 3m
Schedule
96 months past proposed COD
Study Phase
DPP-2016-AUG East (ITC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2018-08-29
MISO-J571 is a proposed 6.4 MW gas-fired generation project located in Kalamazoo County, Michigan. The project was entered into the Midcontinent Independent System Operator (MISO) interconnection queue on May 6, 2016, with a proposed commercial operation date of May 31, 2018. The point of interconnection is the Township of Comstock, County of Kalmazoo, Morrow 138kV.
The project's interconnection agreement (IA) has been executed.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MI
County
Kalamazoo
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Township of Comstock, County of Kalmazoo, Morrow 138kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J571Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.