MISO-J523
50 MW generation in Mower, MN · In queue since November 2015 · Proposed COD September 2021
50 MW
Capacity
1
Components
Solar
10y 8m
In Queue
IA Executed
IA Phase
Signed Mar 2019
Queue → IA
3y 4m
IA → COD
2y 6m
Total Duration
3y 4m
Schedule
59 months past proposed COD
Study Phase
DPP-2016-FEB West
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2021-09-15
MISO-J523 is a proposed 50 MW solar generation project located in Minnesota. The project was entered into the Midcontinent Independent System Operator (MISO) interconnection queue on November 16, 2015, with a proposed commercial operation date of September 15, 2019. The point of interconnection is the ITCM Adams 161 kV Substation.
The project's interconnection agreement has been executed. The developer is listed as MISO.
Generated from interconnection queue and public data sources
Realization history for this asset — final cost vs plan, COD slip vs original date, and construction duration vs cohort. Retrospective context for the operating risk view above. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MN
County
Mower
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
ITCM Adams 161 kV Substation
Data Source
LBNL
Composite operating risk view for this asset — climate hazards across its remaining operating life, observed generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — 10-year P50 trajectory accounting for degradation, observed curtailment, and market conditions, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this asset — 10-year cashflow projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J523Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.